LAPM 2026 · Chapter 14 · Applied Exercises

Ch. 14 — Utility Relocations Applied exercises

1 scenarios1 audit findings2 total exercises
Phase: Applied learning · Worked scenarios · Calculations · Audit findings · Document drills

Apply what you've read — scenario by scenario, calculation by calculation

23 CFR 645 Alternate Procedure, Utility Agreements, prior rights. Each exercise has a hidden solution — work through your answer before revealing.

I
Scenario 01

Prior rights determination

Setup
A federal-aid widening project requires relocation of a 12" PG&E gas main. The gas main has been in its current location, within the street R/W, since 1962. PG&E claims the relocation is at LPA expense (federal-aid reimbursable). The LPA reviews the PG&E franchise agreement, which was executed in 1958 and granted utility easements within the street.
Question
Who pays for the relocation? What governs?
Solution
Likely LPA/federal pays — PG&E's 1958 franchise predates the current relocation need, suggesting "prior rights." Key concept: Prior Rights Determination (23 CFR 645.107 and LAPM Ch 14): • If the utility has compensable property rights (easement, franchise, fee) in the current location predating the public R/W or predating the project, the project bears the relocation cost. • If the utility is in the public R/W under a permit or non-compensable right (terminable at will), the utility bears its own relocation. For PG&E: 1. Franchise from 1958 — granted before the 1962 installation. 2. Gas main installed in 1962, presumably under franchise authority. 3. The franchise grants compensable property rights (typically perpetual easements within public street R/W with relocation reimbursement if the public agency requires relocation). → Likely prior rights. Project pays for relocation. Reimbursable with federal funds if proper documentation. Procedure (23 CFR 645 Alternate Procedure): 1. LPA and utility execute a Utility Agreement before relocation begins. 2. LPA prepares cost estimate; utility provides their cost estimate. 3. LPA submits Utility Agreement to Caltrans for review/approval. 4. FHWA Specific Authorization to Relocate Utilities required (non-delegable, see Ch 2). 5. After authorizations, utility performs work; LPA reimburses utility per Utility Agreement. 6. LPA invoices Caltrans for federal participation in utility relocation costs. If prior rights are unclear — review the franchise carefully and seek legal counsel. Erroneous prior-rights determination is a common audit finding.
Authority: LAPM Ch 14; 23 CFR 645
III
Audit Finding 01

Read the fact pattern — what's the finding?

Facts
An LPA federal-aid project included $187,000 in utility relocation work performed by a private utility. The utility relocation began on March 1, 2026. The Utility Agreement was executed on April 15, 2026. The construction phase E-76 was issued February 1, 2026.
Analysis
What is the finding?
Finding · Citation · Corrective action
Finding: Utility relocation work began before Utility Agreement execution. 23 CFR 645.119(e)(2) and LAPM Ch 14 require: • Authorization to Proceed (E-76) — present here, dated Feb 1. • FHWA Specific Authorization to Relocate Utilities — required and must precede work. • FHWA Approval of Utility Agreement — required and must precede work. Work started March 1; Utility Agreement only executed April 15. The March 1 - April 15 work was performed without authorized agreement in place. Consequence: 1. Work performed before Utility Agreement execution is not federally reimbursable. Verify the date when work actually started — invoices, daily reports. 2. Pre-Award audit finding affecting future federal-aid projects. 3. The utility may have to absorb the costs of pre-agreement work or the LPA may have to pay with non-federal funds. This pattern is common when LPAs feel schedule pressure: they let the utility start under "verbal authorization" with the agreement to follow. That arrangement is not federally compliant. Corrective action: • Ensure all utility agreements are EXECUTED before utility relocation work begins. • If urgency requires expedited utility work, structure interim agreements or use Caltrans expedited review procedures. • Don't rely on the construction-phase E-76 alone — utility relocations have their own authorization chain.
Authority: LAPM Ch 14; 23 CFR 645.119(e)(2)
Applied learning · Companion chapter

These exercises apply the procedural framework presented in LAPM Chapter 14: Utility Relocations. For the full chapter reference, glossary, and recall quiz, see the deep chapter file.